Hazen-Williams friction loss and total dynamic head for temporary bypass pumping and forcemain sizing. Runs entirely offline; inputs persist in this browser via localStorage.
Use limits: This is a field arithmetic aid for sizing temporary pumps and discharge lines, not a substitute for the approved bypass plan or the pump supplier's system analysis. Hazen-Williams applies to full-pipe, turbulent water flow at ordinary temperatures; it does not model sludge, high-solids flow, or air entrainment.
Results at Design Flow
Flow per line
—
Total flow
—
Velocity in line
—
Friction slope
—
Friction loss (one line)
—
Minor losses
—
Total static head
—
Total dynamic head (TDH)
—
TDH in psi
—
System Curve Points
Overlay these on the rental pump's published curve. The operating point is where the curves cross — if the pump curve is above the system curve at design flow, the pump will deliver at least the design flow.
% Design
Total GPM
Velocity (ft/s)
TDH (ft)
How the Numbers Are Derived
Hazen-Williams friction loss
Friction slope in feet of head per 100 ft of pipe, US customary GPM/inch form:
h_f = 0.2083 × (100/C)^1.85 × Q^1.85 / d^4.8655
where Q is flow in GPM in the individual line and d is actual inside diameter in inches. Total friction is the slope times line length divided by 100. Minor losses are applied as a percentage allowance on top of pipe friction.
Velocity and TDH
Velocity: V = 0.4085 × Q / d² (ft/s, Q in GPM, d in inches).
Total dynamic head: TDH = suction lift + discharge static head + friction + minor losses. Conversion to pressure: psi = ft × 0.4331.
HDPE actual inside diameters (common bypass sizes, IPS)
Nominal size is the OD basis for IPS HDPE; the wall (set by DR) eats into the bore. Approximate IDs in inches:
Nominal (IPS)
OD
DR 17
DR 11
4 in
4.500
3.94
3.63
6 in
6.625
5.80
5.35
8 in
8.625
7.55
6.96
10 in
10.750
9.41
8.68
12 in
12.750
11.16
10.29
IDs computed as OD − 2 × (OD/DR), ignoring the small manufacturing tolerance. Verify against the pipe supplier's submittal for the actual material on site.
Velocity guidance for sewage bypass
Minimum: keep velocity at or above roughly 2 ft/s (many specs say 2.5–3.5 ft/s) at the flow that actually runs most of the day, or solids settle in the temporary line and you get grease/rag accumulation and slug discharges.
Maximum: above roughly 8–10 ft/s, friction losses climb steeply, fused joints and restrained fittings see high thrust, and hose whip at the discharge becomes a hazard. It is usually cheaper to go up a pipe size than to buy the head.
Bypass systems sized for peak flow often run at a fraction of peak most of the time — check the velocity at average flow, not just peak.
References
Hazen-Williams empirical formula — standard form per Ten-State Standards and common hydraulics references (e.g. Lindeburg, Civil Engineering Reference Manual).
Plastics Pipe Institute, Handbook of Polyethylene Pipe — HDPE dimensions and C-factor guidance. https://plasticpipe.org/
Manufacturer pump curves — always verify the operating point against the published curve for the specific rental unit.